99% land acquisition for expansion of Khurda-Bolangir railway line completed

Continue reading

July 18, 2024
Odisha Latest

Bhubaneswar: Ninety-nine percent of the required land for the expansion of Khurda-Bolangir railway line project has been acquired. A special team will soon visit the proposed construction site.

Total length of the railway line is 301 Km, of which 183 Km railway line has already been completed. Problems persist over the acquisition of 3.8 Km of land. A patch of around 3.1 Km of land is to be acquired in Nayagarh district and 700 metre of patch in Boudh district, an official source said.

Revenue & Disaster Management department Additional Chief Secretary Satyabrata Sahu today directed the officials concerned to resolve the issues faced by land acquisition within 15 days.

In a high-level meeting held here, the Additional Chief Secretary emphasised adequate compensation to the to-be displaced people in both districts and to ensure their livelihoods through different welfare schemes. Cases pending in courts should be followed up for early disposal, he advised.

Worth mentioning, several senior officials of the Revenue, Forest, Commerce & Transport, and Railway departments took part in the review meeting.

About the Author
728x90 Advertisement

You May Also Like


DISCLAIMER
All content on this website is the exclusive property of Eastern Media Limited. Any downloadable material, including but not limited to electronic or digital versions of the newspaper (e-paper) in any format, is provided solely for personal use. Unauthorized dissemination, distribution, circulation, or publication of any content or e-paper (whether in PDF or other formats) by any means, including on social media platforms, without prior authorization, permission, or license is strictly prohibited.